After standards have been set for materials, labor, and overhead, a standard cost card is prepared. The standard cost card indicates what the cost should be for a completed unit of product.
EXAMPLE:
Referring back to the standard costs computed for materials, labor, and overhead, the standard cost for one jogging suit would be:
Standard Cost Card for Jogging Suits
(1 ) (2)
Standard Standard Standard
Quantity Price Cost
or Hours or Rate (1) x (2)
Direct materials 3.5 yds. $ 6 per yd. $21
Direct labor 2.0 hrs. 18 per hr. 36
Variable manuf. overhead 2.0 hrs. 4 per hr. 8
Total standard cost per suit $65